The words on California public works paperwork, explained in plain English: the apprenticeship forms, preliminary notices and lien waivers JamFile fills.
A
-
Apprenticeship Committee
The body that runs a state-approved apprenticeship program for a craft in an area, often a joint apprenticeship training committee (JATC). On…
C
-
Conditional Waiver
A lien waiver that takes effect only once the payment it describes has actually been received. It is usually sent with the…
D
-
DAS-140
The Public Works Contract Award Information form from California's Division of Apprenticeship Standards. A contractor on a public works job sends it…
-
DAS-142
The Request for Dispatch of an Apprentice form. A public works contractor sends it to an apprenticeship committee to ask for an…
-
Department of Industrial Relations
California's Department of Industrial Relations (DIR). It registers public works contractors and publishes the directory of approved apprenticeship programs by county and…
-
Dispatch Round
JamFile's name for one request for apprentices across a whole job: set the date the apprentices should report, and it prepares a…
-
Division of Apprenticeship Standards
The division of California's Department of Industrial Relations that oversees apprenticeship and publishes the DAS-140 and DAS-142 forms. Both forms are sent…
F
-
Form 119
The California Preliminary Notice for public works of improvement, given under Civil Code sections 8034(b), 8102 and 9300 and following. JamFile fills…
L
-
Lien Waiver
A waiver and release of lien, stop payment notice and payment bond rights, given in exchange for payment. California requires the four…
P
-
Preliminary Notice
A notice given early in a job, often called the 20-day preliminary notice, that protects the right to be paid. It is…
-
Public Works
Construction, alteration, demolition, installation or repair work done under contract and paid for in whole or in part out of public funds,…
-
PWC Registration
The registration number California's Department of Industrial Relations issues to contractors and subcontractors who bid on or work on public works. It…
S
-
Stop Payment Notice
On a California public works job, a claimant who has not been paid cannot record a lien against public property. Instead it…
U
-
Unconditional Waiver
A lien waiver that takes effect when it is signed. The statutory form warns that it is enforceable against the claimant even…